Bikkavolu-Duvvada rail lines: Tenders floated for ₹4,299-crore project to decongest Visakhapatnam

Tenders floated for ₹4,299-crore Bikkavolu-Duvvada rail lines to ease congestion around Visakhapatnam

The South Coast Railway (SCoR) Construction department has initiated the tendering process for constructing the third and fourth broad-gauge Bikkavolu-Duvvada rail lines, near here, at an estimated cost of ₹4,299.12 crore. Spanning 151.08 km from Bikkavolu to Duvvada via Samalkot, the Engineering, Procurement and Construction project covers the Vijayawada and Visakhapatnam divisions. The infrastructure work forms the critical northern leg of the Cabinet-approved ₹9,889-crore Nidadavolu-Duvvada quadrupling corridor along the saturated Chennai-Howrah trunk route.

A pre-bid conference will be held on December 23, 2026, an SCoR official told The Hindu. Bidding opens on February 1, 2027, and closes on February 15, 2027, with a completion period of 45 months. The Ministry of Railways has also initiated a phased land acquisition process under Section 20A of the Railways Act across East Godavari, Dr. B.R. Ambedkar Konaseema, Kakinada, Anakapalli and Visakhapatnam districts.

Cleared by the Cabinet Committee on Economic Affairs in April 2026, the quadrupling corridor is projected to handle an additional 29.04 million tonnes per annum of coal, steel, cement, fertiliser and container freight. The expansion aims to improve punctuality on a trunk route currently operating at nearly 130% capacity.

Key Points Of The Bikkavolu-Duvvada Rail Lines Project

  • Project Cost: Estimated at ₹4,299.12 crore for the Bikkavolu to Duvvada stretch.
  • Corridor Length: Spans 151.08 km covering Vijayawada and Visakhapatnam divisions.
  • Timeline: Pre-bid conference on December 23, 2026; bidding opens February 1, 2027, and closes February 15, 2027, with a 45-month completion period.
  • Freight Capacity: Projected to handle an additional 29.04 million tonnes per annum of freight traffic.

Satellite Stations And Greenfield Bypasses

To eliminate operational bottlenecks in congested urban railheads, the alignment incorporates two major greenfield bypasses. Beyond Annavaram yard, the third and fourth tracks will shift to the upper main line side via a cut-and-connection arrangement, bypassing Timmapuram, Hamsavaram and Tuni stations. A new Tuni Satellite Station will be developed along this bypass before the tracks rejoin the existing corridor roughly 3 km short of Gullipadu station.

Similarly, about 8 km beyond Elamanchili station, the alignment will deviate to bypass Narsingpalli, Bayyavaram, Kasimkota and Anakapalli stations, where a major New Anakapalli Satellite Station will be built. The corridor will rejoin the existing tracks about 1 km before Thadi station before running parallel to the down main line into Duvvada.

Maintenance Hub And Kothavalasa Link Details

To decongest Visakhapatnam Junction and decentralise coaching maintenance, the New Anakapalli Satellite Station is planned with dedicated terminal infrastructure comprising two pit lines and two stabling lines. The new hub will also feature a grade-separated Rail-over-Rail connection linking directly to the alignment toward Kothavalasa.

This link will enable freight rakes moving between the Visakhapatnam-Gangavaram port belt, the Kothavalasa-Kirandul line and the southern coastal corridor to bypass the heavily congested Duvvada-Simhachalam-Visakhapatnam triangle. Officials stated that fresh land acquisition is primarily concentrated along the Tuni and Anakapalli greenfield bypasses, new satellite station yards, and Rail-over-Rail approaches.

The contract also includes crossing stations, high-level platforms, foot-over bridges, 25 kV electrification, electronic interlocking and Kavach train protection across the entire stretch.

Frequently Asked Questions

What is the total estimated cost of the Bikkavolu-Duvvada rail lines project?

The third and fourth broad-gauge railway lines project between Bikkavolu and Duvvada is estimated to cost ₹4,299.12 crore, forming part of the larger cabinet-approved ₹9,889-crore Nidadavolu-Duvvada quadrupling corridor overseen by the South Coast Railway.

When does the bidding process open for the Bikkavolu-Duvvada rail project?

Bidding for the Engineering, Procurement and Construction project opens on February 1, 2027, and closes on February 15, 2027, following a pre-bid conference scheduled for December 23, 2026. The completion period for the 151.08-km stretch is set at 45 months.

<

h5>Stay Updated with the <a style=”


Discover more from Current Affairs World

Subscribe to get the latest posts sent to your email.

You may also like these

Discover more from Current Affairs World

Subscribe now to keep reading and get access to the full archive.

Continue reading